Concrete Cost per m³ in the UK: How a Delivered Price Is Built

Concrete cost per m³ in the UK is the supplier's rate × billed volume, plus part-load, pump, waiting time and 20% VAT. Worked 2.4 m³ slab example inside.

Published 2026-09-19 · Updated 2026-09-19 · BuildMeasure Editorial Team

A 6 m by 4 m slab 100 mm deep worked out as 2.4 cubic metres, beside a stacked quote showing the concrete rate times billed volume, part-load fee, pump, waiting time and 20% VAT adding up to the delivered total.
Original BuildMeasure measurement diagram.

Next step

Turn your measurements into a material estimate

Enter the recorded dimensions in the calculator. It shows the calculated amount, wastage allowance, and a supplier-ready suggested order.

Open the UK Concrete Cost Calculator

How much is concrete per m³ in the UK? Rate × billed m³, plus fees and VAT

Concrete cost per m³ in the UK is not one national figure. A delivered price is the supplier's rate per m³ for your mix multiplied by the volume they bill, plus any part-load or minimum charge, delivery, pump hire and waiting time, then 20% VAT if the quote is ex-VAT. Small orders cost far more per m³ than a full truck.

Published examples show the spread (published prices checked 19 Sep 2026; prices change — get a written quote). Mister Concrete, a London-area supplier, lists C20 at £135, C25 at £139 and C30 at £142 per m³, excluding delivery, additives, offload time and pump hire, with a minimum charge of £625 + VAT. HH Muckers, a volumetric supplier covering Hertfordshire, Essex and north London, advertises from £85 per m³. Neil Sullivan & Sons in Essex lists C25 at £119.80–£182.90 per m³ with a 0.3 m³ minimum for delivery and a £25 + VAT delivery fee.

Because the fees are charged per order rather than per m³, the useful number is the effective cost per m³: the whole delivered total divided by the cubic metres you actually use. The worked example below shows a headline rate climbing by roughly half once fees and VAT are added.

What each line of a UK concrete quote does to the price

Ask every supplier for the same lines so the quotes can be compared like for like. Heidelberg Materials' ready-mixed pricing guide states there is no flat rate and that price depends on the mix, distance, part loads and unloading time; CEMEX's trading terms allow 30 minutes from arrival before a waiting-time charge applies to ready-mixed deliveries.

Lines in a delivered concrete quote and how each one is charged
Quote lineHow it is chargedWhere the figure comes fromIn the 2.4 m³ example below
ConcreteRate per m³ × billed m³Price list or written quote for your mix2.75 m³ × £130 = £357.50
Part-load or short-load feeFlat fee when the order is below a full loadSupplier terms or quote£100
Minimum chargeThe invoice cannot fall below a set totalPrice list (for example £625 + VAT at Mister Concrete)Not applied in this example
Delivery or distancePer load, or by distance from the plantQuoteAssumed included
Pump or conveyorHire by the day or part day, often with travelSeparate pump quote£0 — the truck chute reaches
Waiting timePer period after the free unloading timeTerms (30 minutes at CEMEX; half an hour at Heidelberg)£0 — unloaded within the free time
VAT20% on ex-VAT linesGOV.UK standard rate£91.50

The £130 per m³ rate and £100 part-load fee are illustrative figures you would type into the calculator, not market prices. Copy the real figures from your own written quote.

Worked example: a 6 m × 4 m slab, 100 mm thick

Volume = length × width × depth, all in metres: 6 × 4 × 0.10 = 2.4 m³. Add a 5% allowance for an uneven sub-base and spillage: 2.4 × 1.05 = 2.52 m³. If the supplier sells in 0.25 m³ steps (ask — increments vary), round up: 2.52 ÷ 0.25 = 10.08, so 11 steps = 2.75 m³ ordered and billed.

Using an illustrative rate of £130 per m³ ex-VAT: 2.75 × 130 = £357.50. Add an illustrative £100 part-load fee because 2.75 m³ is well below a full truck (Heidelberg's trucks carry six or eight cubic metres). No pump is needed and the pour finishes within the free unloading time, so those lines are £0. Subtotal ex-VAT = 357.50 + 100 = £457.50. VAT at 20% = 457.50 × 0.20 = £91.50. Delivered total = 457.50 + 91.50 = £549.00.

Effective cost per billed m³ = 549.00 ÷ 2.75 = £199.64, against a headline rate of £130. Per m² of slab it is 549.00 ÷ 24 m² = £22.88. If access forced a line pump quoted at, say, £350 + VAT, the ex-VAT subtotal becomes 457.50 + 350 = £807.50 and the total 807.50 × 1.2 = £969.00, or £40.38 per m². Supplier RMS Concrete publishes line-pump day rates of £275–£450 and boom pumps of £500–£800 (published price checked 19 Sep 2026; prices change — get a written quote).

Slab cost per m²: depth × rate per m³

To turn a price per m³ into a concrete cost per m² of slab, multiply the slab depth in metres by the rate. At 100 mm every square metre holds 0.1 m³, so a £130 per m³ rate is £13.00 of concrete per m². This is the concrete line only: part-load fees, pump, sub-base, formwork, reinforcement, labour and VAT come on top.

Concrete per m² of slab at an illustrative £130 per m³ (concrete line only, ex-VAT)
Slab depthm³ per m²m³ for 10 m²Concrete cost per m² at £130/m³
75 mm0.0750.75£9.75
100 mm0.1001.00£13.00
125 mm0.1251.25£16.25
150 mm0.1501.50£19.50

Cost per m² = depth in metres × rate per m³. Replace £130 with the rate on your own quote. Slab depth for any structural use must come from your designer or building control, not from this table.

Small pours: why 3 m² at 100 mm is a pricing problem

A 3 m² slab at 100 mm is 3 × 0.10 = 0.3 m³. That is below most minimum loads. Heidelberg's mini-mix service (in its northern regions) is described for orders between 0.5 and 3 m³; HH Muckers' volumetric trucks are set up for 1–10 m³ per visit; Neil Sullivan & Sons lists 0.3 m³ as its minimum for delivery (published terms checked 19 Sep 2026).

Minimum charges hit hardest here. At Mister Concrete's published C25 rate, 0.3 m³ would be 0.3 × £139 = £41.70 of concrete, but the published £625 + VAT minimum charge applies instead — about £2,083 per m³ ex-VAT for that pour (625 ÷ 0.3). For pours this size, mixing from cement and all-in ballast or using bagged concrete is usually cheaper: the UK ballast guide's 0.30 m³ example needs about six 25 kg bags of cement and one bulk bag of ballast.

Volumetric (mix-on-site) trucks vs ready-mix drum trucks

A ready-mix drum truck is batched at the plant and brings a fixed quantity. You pay for what is loaded, part loads attract a fee, and any surplus is yours to deal with. Heidelberg notes free delivery on full truck loads, with trucks of six and eight cubic metres.

A volumetric truck carries sand, stone, cement and water in separate compartments and mixes on site, so it stops when you have enough. HH Muckers describes paying per m³ for what is used, with no part-load waste. That suits pours where the volume is uncertain or small. Compare the per-m³ rate, any minimum or call-out charge, and waiting terms from both types before choosing — the lower headline rate is not always the lower delivered total.

  • Ready-mix drum: best value on full or near-full loads; watch part-load fees and returned-concrete charges.
  • Volumetric: pay for the volume actually mixed; useful for small, staged or uncertain pours; check the minimum or call-out charge.
  • Either way: confirm the mix designation, consistence, access for the truck and whether a pump is needed.

VAT on concrete: check the basis of every line

The UK standard VAT rate is 20% and applies to most goods and services. Trade price lists are often ex-VAT, so an ex-VAT rate of £139 per m³ becomes £166.80 once 20% is added (139 × 1.2). HMRC's VAT Notice 708 explains that building materials can be zero-rated when a VAT-registered builder supplies them as part of zero-rated work, such as building a qualifying new dwelling, while retailers and builders' merchants charge the standard rate on most items. Do not assume either: confirm the VAT treatment on each quote.

Common questions

These are the questions UK searchers ask most about the price of concrete per m³.

  • How much is concrete per m3 in the UK? — There is no single national price. Published examples checked on 19 Sep 2026 range from 'from £85 per m³' (volumetric, Hertfordshire/Essex) to £135–£142 per m³ for C20–C30 (London area, excluding delivery). Your delivered total also depends on minimums, part loads, pump and VAT.
  • How much does 1 m³ of concrete cost? — 1 m³ × your quoted rate, plus the per-order fees. On a 1 m³ order those fees are spread across only one cubic metre, so the effective price per m³ is much higher than on a full truck.
  • How much does a 3 m² concrete slab cost? — At 100 mm it is 0.3 m³. Multiply by the rate, then check whether a minimum charge replaces that figure; for many suppliers it will, so bags or a site mix may be cheaper.
  • Does the concrete price include a pump? — Usually not. Mister Concrete's published prices exclude pump hire, and pumps are generally quoted per day or part day.
  • Is volumetric concrete cheaper than ready-mix? — Sometimes. Volumetric charges for what is mixed, which avoids part-load waste; a drum truck can be cheaper per m³ on full loads. Compare the delivered totals.

Same project

Related measurement guides

Sources and limits

Check the project-specific details

  • Mister Concrete — Ready mix concrete pricesSupplier price list: C20 £135, C25 £139, C30 £142, C35 £145, C40 £150 per m³; excludes delivery, additives, offload time and pump hire; minimum charge £625 + VAT (20%). Published price checked 19 Sep 2026; prices change — get a written quote.
  • HH Muckers — Volumetric ready mix concrete (Essex)Volumetric supplier page: 'from £85 per m³', mixed on site, 1–10 m³ per visit, pay only for what is used; VAT basis not stated. Published price checked 19 Sep 2026; prices change — get a written quote.
  • Neil Sullivan & Sons — C25 concreteSupplier product page listing C25 at £119.80–£182.90 per m³, a 0.3 m³ minimum order for delivery and a £25 + VAT delivery fee. Published price checked 19 Sep 2026; prices change — get a written quote.
  • RMS Concrete — Ready mix concrete prices (London)Supplier page quoting line-pump hire at £275–£450 a day and boom pumps at £500–£800 a day, plus waiting-time and small-load charges. Published price checked 19 Sep 2026; prices change — get a written quote.
  • Heidelberg Materials UK — Ready-mixed concrete pricing guideStates there is no flat rate; free delivery on full loads with six and eight cubic metre trucks; part loads charged; half an hour to offload before extra charges; mini-mix for 0.5–3 m³.
  • CEMEX UK — Trading terms and conditionsTerms allowing 30 minutes from arrival before a waiting-time charge on ready-mixed concrete, with part-load and other supplementary charges set out in a separate list.
  • GOV.UK — VAT ratesOfficial source for the 20% standard rate applying to most goods and services.
  • GOV.UK — Buildings and construction (VAT Notice 708)HMRC guidance on zero-rated construction of qualifying new dwellings and when building materials follow that rate; retailers and merchants charge the standard rate on most items.

Review status: Formulas and worked examples checked by hand; measurement practice pending human trade review.

This guide supports planning only. It does not specify structural design, code compliance, or a supplier quotation.